How a Dailey project comes together.

A clear sequence from the first conversation to the final walkthrough. Timing depends on design, approvals, selections, weather, and the scope of your project.

10 steps1 point of contactSite work in-house

Ground to finish

The work behind the finished home.

A look at the stages of construction through real Dailey Homes jobsite photos.

Overhead view of the single-story footprint, with framed rooms and red radiant tubing visible at the edge of the slab.Scioto Bluff · Framing

On site in Delaware County

The first walls at
Scioto Bluff.

From above, you can see where each room will sit.

Follow this single-story custom home from the first excavation to the day the crew stood the walls.

Follow the Ryan build ↗
Consultation
Step 01Week 1

Step 01 · Week 1

Consultation

Meet at our Cardington office or on your site. We talk about what you want to build, how you'll use it, your budget, and your timeline. You'll leave with honest feedback on what's realistic.

You get

  • Budget range
  • Rough timeline
  • Next steps
Site visit
Step 02Week 1–2

Step 02 · Week 1–2

Site visit

We walk the land with you. Access for trucks, slope and drainage, soil, where the well and septic can go, and how far the electric has to run. This is where surprises get caught early.

You get

  • Site notes
  • Utility plan
  • Site-work estimate
Design and selections
Step 032–6 weeks

Step 03 · 2–6 weeks

Design & selections

We draw or adapt your plan, then walk through every selection: cabinets, counters, flooring, siding, roofing, and fixtures. Decisions made here keep the build on schedule.

You get

  • Floor plan & elevations
  • Selections sheet
  • Allowance list
Line-item estimate
Step 04With design

Step 04 · With design

Line-item estimate

You get a written estimate with every category broken out: site work, foundation, framing, mechanicals, finishes, and allowances. Scope, allowances, and selections documented together.

You get

  • Written estimate
  • Payment / draw schedule
  • Contract
Permits and financing
Step 053–6 weeks

Step 05 · 3–6 weeks

Permits & financing

We file permits with the county and township and work with your lender on the draw schedule and inspections.

You get

  • Permits filed
  • Lender paperwork
  • Start date
Site work and foundation
Step 062–4 weeks

Step 06 · 2–4 weeks

Site work & foundation

Our own crew digs, sets footers, pours the foundation, and runs utilities. Site conditions and inspections guide the sequence of this work.

You get

  • Excavation
  • Footers & foundation
  • Utility trenches
Framing and dry-in
Step 073–6 weeks

Step 07 · 3–6 weeks

Framing & dry-in

Walls, trusses, roof, windows, and doors. Dry-in protects the interior so the next stages of work can move forward.

You get

  • Framing walk-through
  • Roof & windows
  • House wrap
Mechanicals and insulation
Step 083–5 weeks

Step 08 · 3–5 weeks

Mechanicals & insulation

Plumbing, electrical, and HVAC rough-ins, inspections, then insulation. We do a walk-through with you before drywall goes up.

You get

  • Rough-in inspections
  • Pre-drywall walk
  • Insulation
Finishes
Step 096–10 weeks

Step 09 · 6–10 weeks

Finishes

Drywall, trim, cabinets, counters, flooring, paint, fixtures, and exterior finishes. This is when it starts to feel like home.

You get

  • Cabinets & tops
  • Flooring & trim
  • Final grading
Walkthrough and keys
Step 10Final week

Step 10 · Final week

Walkthrough & keys

We walk every room with you, make a punch list, and finish it before closing. Then you get your keys, warranty info, and a clean site.

You get

  • Punch list
  • Final inspection
  • Keys